Started the electric to the shop
 
Hi all-

Finally got some time to work on the electric to the new shop.

I got the two meter bases set and the two panels set.

Not much but it is a start.

Steve

http://i1113.photobucket.com/albums/...9F80DE6B3A.jpg

http://i1113.photobucket.com/albums/...18F91830B9.jpg

Mopars 4 Life 10-27-2016 02:31 AM

Awesome dude! Lookin good. 👍🏼👍🏼😎😎

Graham08 10-27-2016 08:21 AM

Cool! Why two meters? Two services to get enough juice?

deaner 10-27-2016 10:43 AM

Three Phase?

Scrambled 10-27-2016 01:20 PM

I wish it was three phase. The electrical company said NO! So I have two 400 amp circuits. The one panel is for a 60 hp phase converter.

Steve

entropy 10-27-2016 03:10 PM

Quote:

Originally Posted by Scrambled (Post 141874)
I wish it was three phase. The electrical company said NO! So I have two 400 amp circuits. The one panel is for a 60 hp phase converter.

Steve

Yup, the electric company said $20,000 minimum and yup, I said NO!

Keep on plugging away! :beer:

Graham08 10-27-2016 04:36 PM

Neat! That's a big RPC. You have pony motor on it to fire it up?

I thought I was bigtime when I got a single 400 amp service to split between the house and the shop...